Block 9 | Tower & Parking Structure
Fargo, ND
Block 9, is a $117 million dollar project consisting of an 18-story mixed use tower along with a total precast parking ramp in the heart of downtown Fargo, North Dakota. The 290,000-square-foot building includes a 125-key boutique hotel run by Aparium Hotel Group; a restaurant; residential condomini… Read More
Wells began erection on the podium portion of the Tower in May 2019, in total, we erected and produced more than 1,690 precast concrete members. This work took approximately 301 working days to complete. The architectural solid precast components on the podium and and the tower boast a beautiful s… Read More
Wells manufactured nearly 220,000 combined sq. ft. of product between the two projects out of our Grand Forks, Albany, and Rosemount production facilities. Beginning February 2019, Wells erected more than 400 precast concrete members for the parking structure, which took approximately 62 working day… Read More
Wells began erection on the podium portion of the Tower in May 2019, in total, we erected and produced more than 1,690 precast concrete members. This work took approximately 301 working days to complete. The architectural solid precast components on the podium and and the tower boast a beautiful s… Read More
Wells began erection on the podium portion of the Tower in May 2019, in total, we erected and produced more than 1,690 precast concrete members. This work took approximately 301 working days to complete. The architectural solid precast components on the podium and and the tower boast a beautiful s… Read More
Wells began erection on the podium portion of the Tower in May 2019, in total, we erected and produced more than 1,690 precast concrete members. This work took approximately 301 working days to complete. The architectural solid precast components on the podium and and the tower boast a beautiful s… Read More
Wells began erection on the podium portion of the Tower in May 2019, in total, we erected and produced more than 1,690 precast concrete members. This work took approximately 301 working days to complete. The architectural solid precast components on the podium and and the tower boast a beautiful s… Read More